|
Eustace ISD Construction Project - Overview
At
a called board meeting held on April 27, 2006, the Eustace ISD Board
of Trustees voted to approve a $7,560,000 building project. The
building project will provide additional classrooms at the High
School and Intermediate School, expansion of the athletic facilities
at the Middle School, and a complete renovation of the Primary
School. RPR Construction Company out of Tyler was awarded the
project. RPR Construction has been in the construction business for
23 years. RPR averages completing about $25,000,000 worth of
construction work a year. They currently have projects underway in
Gilmer ISD, Tyler ISD, as well as several projects at UT Tyler. RPR
also has several non-education related projects underway.
Malcolm McKinley, the district’s architect was at the meeting to
discuss different alternatives available in the building proposals.
Mr. McKinley is employed by the architectural/engineering firm of
Goodwin-Lasiter. Mr. McKinley pointed out that the base bid of
$7,590,000 was below his last estimate of $8,300,000. Several
alternatives were presented to the board for consideration. After
much consideration, the board voted to take the alternatives that
added ceramic tile in the main corridors of the High School and
Intermediate School corridors (+$23,000), to accept the alternative
that added rubber mats in the weight room at the Middle School
(+10,500), to accept the alternative to construct two phases at the
Primary simultaneously (-$20,000), to accept the alternative to omit
the watertight warranty offered with the roof (-$27,000), to accept
the alternative of substituting a laminate finish for stained finish
(-$28,500), and to accept the alternative of adding wall carpet in
the Middle School gym (+12,000). All together, these alternatives
actually lowered the final cost of the construction project by
$30,000.
The
awarding of the bid at last night’s board meeting was the
culmination of almost two years of work by the board and by citizens
in the community that served on the Construction Committee. The
Construction Committee began meetings in September of 2004 that
continued through October of 2004. The Construction Committee spent
many hours talking with financial advisors, talking with the
district’s architect and reviewing the needs of the district. The
Construction Committee unanimously voted to recommend to the Board
of Trustees a $13 million bond project to be broken apart in two
phases. The first phase, $9 million, was to consist of taking care
of immediate academic needs throughout the district and providing
additional space for athletics at the Middle School. The second
phase, $4 million, was to be based on the district receiving state
funding to help offset the cost of the first phase. The second phase
was to consider the building of a new competition gym for the High
School.
The
Board of Trustees voted to accept the recommendation of the
Construction Committee and called for a bond election in February
2005. The bond project was approved by the voters of Eustace ISD.
Following the bond election, work with our architect and engineer
began in earnest. Several different plans were considered and many
modifications were made to ensure that the district would get the
most construction for every dollar spent. In February, the board
gave final approval to the plans.
Below is a breakdown of all major projects that will be completed
with this bond package:
|
$7,590,000 |
Lowest Base
Bid on Major Construction Project |
|
$23,000 |
Ceramic Tile |
|
$10,500 |
Rubber Mats |
|
-$20,000 |
Construct A
& B simultaneously |
|
-$27,000 |
Omit
Warranty |
|
-$28,500 |
Stain to
Laminate |
|
$12,000 |
Wall Carpet
in Gym |
|
$7,560,000 |
Total Cost
of Project |
|
|
|
|
$278,000 |
Remainder of
Architect Fee |
|
$423,000 |
Estimated
Cost of Bus Barn |
|
$95,000 |
Cost of AC
Projects at IS and PS Gyms |
|
$119,000 |
Estimated
Costs of Renovations at High School |
|
$100,000 |
Estimated
Cost to Renovate Existing Maintenance Building to Add Classrooms |
|
$270,000 |
Estimated
Costs to Supply and Furnish New Classrooms |
|
$5,400 |
Estimated
Cost of 1/2 to Close in Porch in HEC |
|
$8,850,400 |
|
|
|
|
Note that the cost of the bus barn is an estimate. Bids for the bus
barn have not yet been solicited. Also, note that the estimated
total cost of all the projects listed is $8,850,400. Even though the
district has already completed renovations on the old administration
building and moved special services into this building and installed
new air-conditioning units in the high school, we currently have
available approximately $8,900,00 from our bond sale. Taking into
account that the district actually received less than $9,000,000
from the bond sale because of fees and taking into account the
renovations already completed, having about $8,900,000 available for
all of these other projects puts the district in a very positive
position. It is estimated that by the time the major payments are
being made the district will have available approximately $9,000,000
for this project (the increase comes from accrued interest).
Back
..........................................................................
Summary
of Projects
High School Renovations
and Additions:
 |
Addition of 9 new
classrooms and 1 science lab |
| |
 |
Including
additional student desks, computers, teacher desks and filing
cabinets, network wiring, computer workstations, and TVs
|
 |
Replace original carpet in corridors with ceramic tile |
 |
Replace original carpet in classrooms and library |
 |
Paint
the interior of the building |
 |
Replace ceiling tiles as needed |
 |
Enclose the “porch” in the food science classroom for
additional classroom space |
 |
Install new air-conditioner units at the high school (already
completed) |
| |
|
Middle School Renovations
and Additions
 |
Renovation of existing special
services building to house new classrooms |
 |
Addition of new locker room |
 |
Addition of new practice gym |
 |
Addition of new weight room |
Intermediate School
Renovations and Additions
 |
Addition of 7 new
classrooms |
| |
 |
Including
additional student desks, computers, teacher desks and filing
cabinets, network wiring, computer workstations, student
chairs and TVs |
 |
Addition of new cafeteria seating area |
| |
 |
Including tables
for seating |
 |
Air-conditioning of the Intermediate School Gym |
Primary School
Renovations and Additions
 |
Addition of 20 new
classrooms |
| |
 |
Including
additional student desks, computers, teacher desks and filing
cabinets, network wiring, computer workstations, student
chairs, student tables, and TVs |
 |
Addition of new
media center |
 |
Enclosing walkways
|
 |
Renovating and
reconfiguring the entrance and office area |
 |
Air-conditioning
of the Primary Gym |
District Improvements
 |
Addition of a new bus barn |
 |
Renovation of old bus barn for
maintenance department |
 |
Renovation of old
administration building (already completed) |
Back
..........................................................................
Architect/Engineer
Engineer/Architect: Goodwin-Lasiter, Lufkin,
Texas
Lead Engineer:
Larry Lasiter
Architect:
Malcolm McKinley
Goodwin-Lasiter, Inc. is one of the largest firms in the East Texas
Region, with a staff of 44 employees, including 19
professional-level staff members. Our professional staff includes 8
registered engineers, 5 registered professional land surveyors, 1
surveyor-in-training, 2 registered architects, 2
engineers-in-training, and 2 intern architects. Engineering
registration is currently maintained in the states of Texas,
Oklahoma, Arkansas and Kentucky. Surveying registration is
currently maintained in Texas. Architectural registration is
maintained in Texas.
The
staff has a combined professional experience of over 100 years, with
expertise in civil engineering, structural engineering, sanitary
engineering, mechanical/electrical/plumbing engineering,
architecture, surveying, and planning. Our business has enjoyed
continual growth because we have been able to provide clients
building projects that fit their needs, budgets and schedules.
Because Goodwin-Lasiter, Inc. is a multi-discipline firm, we can
staff projects to meet the time demands of our clients projects.
Planning, Design and drafting are produced using
"state-of-the-industry" computer-aided systems. Surveying data is
presented in Geopak/Microstation or Maptech/Autocad format.
Back
..........................................................................
Financial Advisor
Doug Whitt, Senior Vice
President
Southwest
Securities, Plano, Texas
Back
..........................................................................
Construction Contractor
RPR Construction
Company, Tyler, Texas
RPR
Construction has been in the construction business for 23 years. RPR
averages completing about $25,000,000 worth of construction work a
year. They currently have projects underway in Gilmer ISD, Tyler ISD,
as well as several projects at UT Tyler. RPR also has several
non-education related projects underway.
Back
..........................................................................
Timeline
RPR
Construction submitted their proposal based on an 18 month
construction schedule.
Back |